TRANXACT.AI Training

Mission control: who does what

The two named owners and the crew, the RACI across the countdown, the 15-minute standup, the Fit Ledger, scope triage and the countdown board.

The method · 18 minutes · 5 questions

For: Countdown Owners, Flight Leads, key users, and executives who will be invited to a standup.

There is no monthly steering committee and no status deck. There is one 15-minute standup a day, customer and TRANXACT together, in front of the countdown board and the live tenant — and decisions are made the same day, because overnight waits are the enemy of the clock.

Two named owners

RoleSideOwns
Countdown OwnerCustomerSame-day authority on scope; signs the Fit Ledger and the go / no-go
Flight LeadTRANXACT — the AI Deployment OrchestratorRuns the board and the standup; protects the date
Ledger ArchitectTRANXACTConfiguration design, integrations, Fit Ledger patterns
Data Migration ConductorTRANXACTMigration Cockpit, mocks, reconciliation, cutover runbook
Autonomous Operations PilotTRANXACTTenant, SSO, environments, dry-run and go-live operations
AI Adoption NavigatorTRANXACTQueues, ASK, coaching in the flow, adoption and change
Key users — one per processCustomerDiscover by doing, validate configuration, run the rehearsal
Finance controller and data ownersCustomerCleanse data; sign reconciliations and opening balances

The Countdown Owner must be able to make scope calls the same day without escalation. If that person does not exist, the countdown should not start.

The RACI in one line

The Countdown Owner is Accountable for everything. Responsibility moves with the work: the Flight Lead and Ledger Architect for the Fit Ledger, the Ledger Architect and key users for configuration, the Migration Conductor for mocks and reconciliation, the Flight Lead, Conductor and Ops Pilot together for the runbook and dry run, the Adoption Navigator and key users for adoption and change and for the rehearsal.

The daily 15-minute standup, to scale 2 minWhere are we?T-day, days left,gate ahead4 minYesterdayDone against plan, shown in the tenant4 minTodayWorkstream focus and sessions3 minBlockersOwner and time to clear,today2 minScope callsFit Ledgerdecisions taken now
The daily 15-minute standup, to scale
  • Same time every working day, T-0 included; both owners present or delegated in writing.
  • No slides: the board, the Fit Ledger and the tenant only; decisions logged in the Toolkit’s Countdown Board sheet.
  • Problem-solving moves to a named break-out afterwards — the standup records the scope call and its owner, nothing more.
  • After go-live it becomes the hypercare standup on yesterday’s exceptions.

The Fit Ledger replaces the requirements document

One public line per gap found on a screen: what is on screen, what is needed, the decision, the configuration pattern or wave, and the owner. Once the Countdown Owner signs a decision it is not reopened; a change of mind becomes a new line with a new date.

Scope triage: configure now, T-Plus or not needed Gap on screen (FitLedger line)Is it a real businessneed?Configurable no-code?Configured and rehearsedbefore T-3?Configure nowT-Plus waveNot neededPattern, T-Plus or anhonest noYesYesYesNoNoNoRule 3 applies at the second question: code goesthrough the extension framework, never through thecountdown.
Scope triage: configure now, T-Plus or not needed

Rule 3 applies at the second question: if it needs code, the answer is a configuration pattern, T-Plus, or an honest no — the extension framework, never the countdown. A gap that cannot be configured and rehearsed before T-3 goes to T-Plus automatically, unless the Countdown Owner drops something else to make room.

The countdown board

One page for everyone: working days to go-live, the next gate, percent complete and a line of status per workstream, and the Fit Ledger totals. It is mirrored from the Project Plans dashboard, so days left come from the go-live date and status rolls up from every source-system plan.

Calderwood Group — the worked example

Calderwood at T-12: 64 Fit Ledger lines — 41 configure now, 15 T-Plus, 8 not needed. Testing is at 55% because integration tests start at T-10; the board shows it in red, and the standup records who owns clearing it rather than debating it.

Try it At T-9 the finance team asks to reopen FL-004 — the legacy "daily cash v7" report, signed off as Not needed at T-20. What happens?

The signed line is not reopened. If the need is real, it becomes a new Fit Ledger line with today’s date and goes through triage: with T-3 so close, the likely outcomes are that the dashboard still covers it, or it goes to T-Plus — unless the Countdown Owner drops something else to make room.

Check what you know